A cargo tank with a test due may not be filled. Under 49 CFR 180.407(a)(1), a cargo tank for which a test or inspection has become due may not be filled and offered for transportation or transported until the test has been successfully completed. This tool works out the next due date for every test on your tank, from the intervals in the table in section 180.407(c), so the due date never catches you at the loading rack.

Read the specification from the plate on the tank, then answer the service questions and enter the last test dates from the test reports. Leave a test date blank when the tank has never had that test: the tool counts from the CTMV certification date instead. Every answer updates the result as you change each field. Enter dates as YYYY-MM-DD.

About the tank

Vacuum loading shortens the external visual inspection to 6 months plus the pressure test to 2 years. Insulation shortens the internal visual inspection to 1 year on most specifications, plus the pressure test to 1 year when the tank has no manhole or is lined. A tank with no manhole takes a pressure test instead of an internal visual inspection.

Service

Answer the chlorine, propane, plus sodium questions only when they describe this tank. They change the schedule only for MC 330 and MC 331 tanks. The 10 year propane interval also covers NQT SA-202 and NQT SA-455 steel with qualifying Charpy test data.

Condition triggers

Damage and long time out of service trigger tests on their own, whatever the periodic schedule says. Damage that may affect lading retention triggers a pressure test, plus a thickness test of each damaged area. A year or more out of hazardous materials service triggers a pressure test before further use.

Dates

The certification date is the baseline for any test with no date entered. Set the check date to today before relying on the result.

Read the last test dates from the test reports or from the markings near the specification plate. The markings show the month and year each test passed, plus the letter for the test: V, I, L, K, P, or T.

Verdict: Do not load.

2 tests overdue, 2 tests due soon, 0 tests current, 3 not applicable.

2 tests on this cargo tank are overdue or due now. Under section 180.407(a)(1) the tank may not be filled and offered for transportation or transported until every due test has been successfully completed. Book the overdue tests now, before the tank takes another load.

The tests

TestStatusDetail
External Visual Inspection (V)Due soonLast test: November 20, 2025 (last test date). Interval: 1 year, 1 year row for all other cargo tanks. Next due: November 20, 2026. Due in 1 day.
Internal Visual Inspection (I)OverdueLast test: June 15, 2021 (last test date). Interval: 5 years, 5 year row for all other cargo tanks, except MC 338. Next due: June 15, 2026. Overdue by 157 days.
Lining Inspection (L)N/AThis tank is not lined, so no lining inspection applies. A lined tank needs its lining verified at least once each year under section 180.407(f).
Leakage Test (K)Due soonLast test: November 20, 2025 (last test date). Interval: 1 year, 1 year row for all other cargo tanks, except MC 338. Next due: November 20, 2026. Due in 1 day.
Pressure Test (P)OverdueLast test: June 15, 2021 (last test date). Interval: 5 years, 5 year row for all other cargo tanks. Next due: June 15, 2026. Overdue by 157 days.
Thickness Test (T)N/AThe thickness test in section 180.407(i)(1) applies to unlined cargo tanks transporting material corrosive to the tank. This tank does not carry corrosive lading.
Heating System Pressure Test (P)N/AThis tank has no heating system, so the 5 year heating system test in section 180.407(g)(4) does not apply.

The figures

FigureValueNote
Tank specificationDOT 406Low pressure tank for flammable liquids, including gasoline and diesel.
Service profileGeneral serviceVacuum loading, insulation, lining, plus lading each change one or more intervals in the table in section 180.407(c).
CTMV certification dateJune 15, 2021The retest date is counted from the most recent inspection, or from the certification date where no test date was entered, under section 180.407(c).
Check as ofNovember 19, 2026Overdue and due soon are measured against this date. Set it to today before relying on the result.
Earliest due testInternal Visual Inspection (I), June 15, 2026The test that falls due first. Book it before the date shown, or before further use when it is due now.
Tests overdue2A test counts as overdue when its due date has passed, or when a condition in section 180.407(b) makes it due now.
Markings on the tankV, I, K, PAfter each test is passed, the tank is marked near the specification plate with the letter for the test plus the month and year, in letters at least 32 mm (1.25 in) high, under section 180.415. Example: a pressure test passed in November 2026 is marked P 11-26.
Pressure test pressureNameplate pressure, 5 psig, or 1.5 times the MAWP, whichever is greaterSection 180.407(g)(1)(iv). At no time during the pressure test may the tank be subject to a pressure above the figure in the table.

What to do

  • Book the Internal Visual Inspection (I) now. The tank may not be filled or offered for transportation until it passes, under section 180.407(a)(1).
  • Book the Pressure Test (P) now. The tank may not be filled or offered for transportation until it passes, under section 180.407(a)(1).
  • Book the External Visual Inspection (V) before its due date, so the tank never sits idle waiting on a test.
  • Book the Leakage Test (K) before its due date, so the tank never sits idle waiting on a test.
  • Until every overdue test passes, do not load the tank. A tank filled before a due date may finish that trip, but it may not be filled again until the test passes.
  • Keep the test reports on file until the next test of the same type is passed, under section 180.417(b)(3).

Records and markings to keep

  • Keep each test and inspection report until the next test or inspection of the same type is successfully completed, under section 180.417(b)(3).
  • Keep the manufacturer certificate for as long as you own the tank, plus one year after, under section 180.417(a)(1). A buyer or lessee must be given a copy of the certificate, the repair records, plus the most recent test reports.
  • Check the markings after every test: the letter for the test plus the month and year, at least 32 mm (1.25 in) high, near the specification plate or anywhere on the front head.
  • A tank that fails a test must be repaired and retested under section 180.413, or taken out of hazardous materials service with the specification plate removed, obliterated, or covered in a secure manner.
  • The annual vehicle inspection under section 396.17 is separate from these tank tests. Track it on the Annual Inspection Due-Date Tracker, so the truck inspection stays current alongside the tank schedule.

Notes

  • When more than one row of the table in section 180.407(c) applies to the same test, this tool uses the shortest interval. That is the safe reading: the test that falls due first is the one that governs the tank.
  • A cargo tank filled before a test due date may finish that trip. Section 180.407(a)(1) bars filling and offering for transportation after the due date, not the transport of a load taken on before it.
  • The leakage test pressure must be no less than 80 percent of the MAWP marked on the specification plate, held for at least 5 minutes, under section 180.407(h)(1). Dedicated LPG and anhydrous ammonia MC 330 and MC 331 tanks may test at not less than 60 psig.
  • A petroleum distillate fuel tank with vapor collection equipment may take its leakage test under EPA Method 27, marked K-EPA27, under section 180.407(h)(2).
  • Only a Registered Inspector meeting the qualifications in section 180.409 may perform or witness these tests, plus each tank must be evaluated against the acceptance criteria in section 180.411.

This tool applies 49 CFR 180.407 to your inputs. Confirm the result against the regulation text plus the test reports before acting. A wrong last test date gives a wrong due date, so check each date against the report before relying on it.

Your inputs stay in this browser. Nothing is sent to our servers. There is no account to create.

Disclaimer: This tool is a planning estimate based on the published text of 49 CFR 180.407, not legal advice — confirm the result plus any test date with a Registered Inspector, PHMSA, or your legal counsel before relying on it at the loading rack.

Quick answer: A specification cargo tank needs up to seven periodic tests under 49 CFR 180.407: external visual every year, internal visual every 5 years, lining every year on lined tanks, leakage every year, pressure every 5 years, thickness every 2 years on unlined tanks hauling corrosive lading, plus heating system pressure every 5 years where fitted. The intervals shorten for vacuum loading, insulation, corrosive lading, plus chlorine service, plus they stretch to 10 years for a small MC 331 propane tank. A tank with a test due may not be filled until the test passes.

Last reviewed: · Focus keyword: cargo tank inspection schedule

How often does each cargo tank test fall due?

A specification cargo tank lives on a schedule set by federal regulation, not by the carrier maintenance plan. Section 180.407 of Title 49 of the Code of Federal Regulations sets the tests, the intervals, plus the consequences of missing one, for every DOT specification cargo tank in hazardous materials service: DOT 406, DOT 407, DOT 412, plus the older MC 306, MC 307, MC 312, MC 330, MC 331, plus MC 338 tanks still on the road. A tank that misses a test date is not merely overdue for maintenance: it is barred from loading until the test passes.

The regulation lists six tests in the table in paragraph (c), plus a seventh in paragraph (g)(4): external visual every year, internal visual every 5 years, lining every year on lined tanks carrying corrosive lading, leakage every year, pressure every 5 years, thickness every 2 years on unlined tanks carrying corrosive lading, plus heating system pressure every 5 years where fitted. Service conditions shorten several of them, which is why two identical tanks on different work can sit on different schedules.

TestMarkingBase intervalWhat shortens it
External visual inspectionV1 year6 months for vacuum-loaded tanks with full opening rear heads
Internal visual inspectionI5 years1 year when insulated, except MC 330, MC 331, MC 338, or when the lading is corrosive to the tank
Lining inspectionL1 yearApplies to lined tanks carrying corrosive lading; lining integrity verified yearly where lining is required
Leakage testK1 year2 years for MC 330 and MC 331 in chlorine service; no row for MC 338
Pressure testP5 years1 year when insulated with no manhole or insulated and lined, except MC 338; 2 years for vacuum-loaded tanks plus MC 330 and MC 331 in chlorine service
Thickness testT2 years1 year once the reading falls below minimum thickness plus one-fifth of the original corrosion allowance
Heating system pressure testP5 yearsNo shorter interval in the regulation

Every due date counts from the same starting point. Paragraph (c) states that the retest date is determined from the interval in the table, counted from the most recent inspection or the CTMV certification date. A tank tested on June 15, 2021, with a 5 year pressure test interval, falls due on June 15, 2026. A tank that has never had a given test counts from its certification date, the date on the specification plate. That is why this tool asks for the certification date first: it is the baseline for every blank test date.

One reading question comes up whenever a tank falls under two rows of the table at once. An insulated tank carrying corrosive lading matches both 1 year internal visual rows. A vacuum-loaded MC 331 in chlorine service matches two 2 year pressure test rows. The regulation does not rank the rows. This tool uses the shortest interval whenever more than one row applies to the same test. That is the safe reading, because the test that falls due first is the one that governs the tank, plus meeting the shortest interval always satisfies the longer one.

The schedule is only half of the compliance picture. A tank that passes every test still needs a driver qualified to haul it, with the tank vehicle endorsement, the N endorsement, on the commercial driver license. The Hazmat Load / Endorsement Checker works out whether a driver with a given set of endorsements may legally haul a described load, including tank vehicle loads. The CDL Endorsement Checker covers which endorsements a driver needs for the vehicle, plus the Hazmat Endorsement Cost Checker works out the cost and timeline for the H endorsement. For the load itself, the Tanker Load Calculator works out tanker load weight, axle weights, plus the most that can legally be loaded.

What happens when a cargo tank test falls due?

The consequence is written into the first paragraph of the section, plus it is absolute. Section 180.407(a)(1) states that a cargo tank constructed under a DOT specification, for which a test or inspection specified in the section has become due, may not be filled and offered for transportation or transported until the test or inspection has been successfully completed. There is no grace period plus no short trip home: once the due date passes without a passed test, the tank stays empty until a Registered Inspector passes it.

The paragraph carries one exception, plus it matters at dispatch time. The bar does not apply to any cargo tank filled prior to the test or inspection due date. A tank loaded on June 14, with a test falling due on June 15, may finish that trip. The load was taken on before the due date, so the regulation does not strand it. The same tank may not be filled again on June 16, June 17, or any later day until the test passes. Dispatchers who run tanks close to their due dates should plan the last load to end before the due date, with the test booked for the day the tank comes back empty.

A failed test brings a second consequence. Section 180.407(a)(6) gives the owner two options when a cargo tank fails a prescribed test or inspection: repair it and retest it in accordance with section 180.413, or remove it from hazardous materials service and remove, obliterate, or cover the specification plate in a secure manner. There is no third option. A repair affecting structural integrity must be proven by the testing in the manufacturing specification or in section 180.407(g)(1)(iv). Use the FMCSA Fine Calculator to work out the current penalty for a given violation, plus check the current appendix before quoting a figure, because the amounts move with inflation rules.

The thickness rule has its own version of the same fork. Section 180.407(i)(6) lets an owner keep using a tank below the minimum thickness for its design, but only at reduced maximum weight of lading or reduced maximum working pressure, or both, certified by a Design Certifying Engineer through a revised manufacturer certificate, with the nameplate changed to show the revised limits. Section 180.407(i)(7) closes the door further: a tank that no longer conforms with the minimum thickness for the specification may not return to hazardous materials service at all.

The practical answer is to treat the earliest due date as the tank deadline, not the latest. This tool names that test in the figures table, so the maintenance plan can book the earliest test first and bundle the others around it. Many carriers line up the annual external visual inspection with the annual leakage test, since both run on a 1 year cycle, plus line up the 5 year internal visual inspection with the 5 year pressure test, since the pressure test itself includes an external and internal visual inspection under paragraph (g)(1)(i). Bundling early is fine, bundling late is not.

How does the tank specification change the schedule?

The specification on the plate decides which rows of the table apply, which pressure the tank is tested to, plus, for the older MC tanks, whether the tank can still be certified at all. The nine specifications this tool covers fall into three families: the DOT 400 series, DOT 406, DOT 407, plus DOT 412, the current low pressure specifications; the MC 300 series, MC 306, MC 307, plus MC 312, their predecessors; plus MC 330, MC 331, plus MC 338, the high pressure and cryogenic specifications, each with its own service rules.

The change from MC to DOT specifications is dated by regulation, not by industry habit. Section 180.405(b)(1) states that no cargo tank may be marked or certified after August 31, 1995, to the MC 306, MC 307, MC 312, MC 331, or MC 338 specification in effect on December 30, 1990. The older MC 306, MC 307, plus MC 312 tanks still on the road were certified before the cutoff, plus they stay in service under their original specifications. Section 180.405(b)(2) lets an MC 306, MC 307, or MC 312 tank be recertified to its original specification, provided records verify the original manufacture, a Design Certifying Engineer or Registered Inspector verifies conformity, the tank passes the tests in section 180.407(c), plus the recertification is recorded under section 180.417.

MC 338 is the specification that most often surprises a buyer, because the table treats it differently from every other tank. The internal visual inspection row for all other cargo tanks excepts MC 338. The leakage test row excepts MC 338. The thickness test row excepts MC 338. The 1 year pressure test row for insulated tanks with no manhole or insulated and lined excepts MC 338. What remains is the annual external visual inspection plus the 5 year pressure test on the all other cargo tanks row, which carries no MC 338 exception. The reason is the design: an MC 338 is a vacuum insulated cryogenic tank, built to hold oxygen, nitrogen, argon, or LNG at very low temperature, plus its inner vessel cannot be opened for routine internal inspection the way a fuel tank can. Paragraph (g)(1)(i) confirms the approach: as part of the pressure test, the inspector must perform an external and internal visual inspection, except that on an MC 338 cargo tank, or a cargo tank not equipped with a manhole or inspection opening, an internal inspection is not required.

The one exception to the MC 338 pattern is corrosive lading. The internal visual row for all cargo tanks transporting lading corrosive to the tank carries no MC 338 exception, so an MC 338 hauling corrosive lading takes an annual internal visual inspection like any other tank. In practice the combination is rare, because cryogenic liquids are not ordinarily corrosive to the tank, but the table reads the way it reads, plus this tool applies it literally.

MC 330 and MC 331 carry the most service-specific rules of any specification. They are the high pressure tanks, built for compressed gases, liquefied petroleum gas, anhydrous ammonia, plus chlorine. Chlorine service stretches their leakage test plus pressure test to 2 years. Dedicated propane service on a small MC 331 stretches the internal visual inspection plus the pressure test to 10 years. Dedicated sodium metal service removes the pressure test entirely. Section 180.407(g)(3) adds a wet fluorescent magnetic particle inspection before and with the pressure test for quenched and tempered MC 330 and MC 331 tanks in anhydrous ammonia, LPG, or corrosion stress cracking service, plus for non-quenched and tempered tanks without postweld heat treatment in ammonia or stress cracking service.

The pressure test pressure itself varies by specification, under the table in paragraph (g)(1)(iv). At no time during the pressure test may a tank be subject to a pressure above the figure in the table. The test pressure is the nameplate pressure, a floor figure, or a multiple of the design pressure or MAWP, whichever is greater, except for MC 330, MC 331, plus MC 338, where it is a multiple of the MAWP or the re-rated pressure.

SpecificationPressure test pressure
MC 306Nameplate pressure, 3 psig, or design pressure, whichever is greater
MC 307Nameplate pressure, 40 psig, or 1.5 times design pressure, whichever is greater
MC 312Nameplate pressure, 3 psig, or 1.5 times design pressure, whichever is greater
MC 330, MC 3311.5 times the MAWP or the re-rated pressure, whichever applies
MC 3381.25 times the MAWP or the re-rated pressure, whichever applies
DOT 406Nameplate pressure, 5 psig, or 1.5 times the MAWP, whichever is greater
DOT 407Nameplate pressure, 40 psig, or 1.5 times the MAWP, whichever is greater
DOT 412Nameplate pressure or 1.5 times the MAWP, whichever is greater

What changes when a tank loads by vacuum, is insulated, or is lined?

Three construction and operating facts move the schedule more than any others: whether the tank loads by vacuum, whether it is insulated, plus whether it is lined. Each one changes at least one interval, plus the three together can turn a 5 year pressure test into a 1 year pressure test. The questions in the tool exist because the table in paragraph (c) is written around these facts, not around the specification alone.

Vacuum loading is the hardest on the schedule. A cargo tank designed to be loaded by vacuum with a full opening rear head takes an external visual inspection every 6 months, not every year, plus a pressure test every 2 years, not every 5 years. The reason is the rear head itself: a full opening rear head is a large closure that opens for loading, plus its gasket is a leak path that needs watching. Paragraph (d)(6) requires the gaskets on any full opening rear head to be visually inspected for cracks or splits caused by weather or wear, plus replaced when cuts or cracks likely to cause leakage, or of a depth one-half inch or more, are found. The 6 month external visual inspection is the regulation way of keeping that gasket under regular eyes.

Insulation changes the internal visual inspection first. All insulated cargo tanks, except MC 330, MC 331, plus MC 338, take an internal visual inspection every year instead of every 5 years. The reason is straightforward: insulation hides the outside of the shell, so corrosion under the insulation cannot be seen from the outside, plus the internal inspection becomes the check that finds it. Paragraph (d)(1) makes the same point from the other direction: where insulation precludes a complete external visual inspection, the cargo tank must also be given an internal visual inspection.

Insulation changes the pressure test too, in one specific combination. All cargo tanks which are insulated with no manhole or insulated and lined, except MC 338, take a pressure test every year instead of every 5 years. An insulated tank with a manhole and no lining stays on the 5 year pressure test row. When the inspector cannot see inside the tank and cannot see the shell under the insulation, the pressure test becomes the check that proves the tank still holds, plus it runs yearly.

Note 4 softens the insulated tank rules for tanks that do have access. Insulated cargo tanks equipped with manholes or inspection openings may take an internal visual inspection with the external visual inspection, or a hydrostatic or pneumatic pressure test instead. Either path satisfies the annual check. This tool applies the table row for the internal visual inspection and notes the Note 4 option in the results.

Lining brings its own test. The table sets a 1 year lining inspection for all lined cargo tanks transporting lading corrosive to the tank, plus paragraph (f) requires the integrity of the lining on all lined cargo tanks, when lining is required by the subchapter, to be verified at least once each year. Rubber lining is tested for holes with a high frequency spark tester, calibrated against a steel coupon covered with the same material and thickness. Linings made of other material are tested using equipment and procedures prescribed by the lining manufacturer or installer. Degraded or defective areas of the liner must be removed, the tank wall below the defect inspected, plus corroded areas of the wall thickness tested.

Lining also creates the one pressure test exception that owners most often miss. Note 3 states that pressure testing is not required for uninsulated lined cargo tanks, with a design pressure MAWP of 15 psig or less, which receive an external visual inspection and lining inspection at least once each year. All three conditions must hold: uninsulated, lined, plus MAWP at or under 15 psig, with both annual inspections actually performed. An insulated lined tank does not qualify. A lined tank with a higher MAWP does not qualify. This tool applies the exception only when all three conditions are answered yes, plus it still requires a pressure test when damage or time out of service triggers one under paragraph (b).

The manhole question matters on its own. Paragraph (e)(1) states that when a cargo tank has no manhole or inspection opening, or its design precludes an internal inspection, the tank shall be hydrostatically or pneumatically tested instead. A tank with no manhole has no internal visual inspection row in this tool: the result marks it not applicable and points at the pressure test schedule. Section 180.405(g)(1) requires conforming manhole assemblies on MC 306, MC 307, plus MC 312 tanks marked or certified after December 30, 1990, plus on all DOT 406, DOT 407, plus DOT 412 vehicles, so a modern DOT tank without a manhole is unusual, but older tanks plus some special designs still lack one.

What does corrosive lading change?

Corrosive lading is the single service fact that touches the most tests. A tank carrying material corrosive to the tank takes an annual internal visual inspection instead of a 5 year one, an annual lining inspection when lined, a thickness test every 2 years when unlined, plus two extra inspection duties outside the main table. The regulation treats corrosion as a clock: the metal thins while the tank works, plus the schedule is built to catch the thinning before it reaches the minimum.

The internal visual inspection is the first change. The table sets a 1 year interval for all cargo tanks transporting lading corrosive to the tank, with no specification exception. That row reaches MC 338 tanks, which no other internal visual row reaches. The inspection covers the tank shell and heads for corroded and abraded areas, dents, distortions, defects in welds, plus any other unsafe condition, plus it includes the liner inspection under paragraph (f) where the tank is lined.

The thickness test is the second change, plus it is the test that measures the corrosion directly. Paragraph (i)(1) requires the shell and head thickness of all unlined cargo tanks used for the transportation of materials corrosive to the tank to be measured at least once every 2 years, except that cargo tanks measuring less than the sum of the minimum prescribed thickness, plus one-fifth of the original corrosion allowance, must be tested annually. The one-fifth rule is the tripwire: once the wall thins to within one-fifth of the corrosion allowance above the minimum, the test interval halves to a year. Measurements must be made with a device accurate to within plus or minus 0.002 of an inch, operated by a person trained in its use per the manufacturer instruction.

The thickness test covers ten areas of the tank wall at a minimum, listed in paragraph (i)(4): the shell and heads plus the area around lading piping; high stress areas such as the bottom center; areas near openings, weld joints, shell reinforcements, plus appurtenance attachments; areas near upper coupler and suspension attachments; known thin areas plus nominal liquid level lines; and connecting structures joining multiple carbon steel tanks in a self-supporting vehicle. A thickness test that skips the bottom center or the weld joints has skipped the areas where corrosion bites first.

Minimum thickness is defined by specification. For MC 300 series tanks, paragraph (i)(5) sets in-service minimum thicknesses at 90 percent of the manufactured thickness in the DOT specification, rounded to three places, with tables for steel plus aluminum. For MC 331 tanks built before October 1, 2003, it is the U1A form thickness minus any corrosion allowance; for later MC 331 tanks, it is the value on the specification plate. For 400 series tanks, it comes from the tables in sections 178.346-2, 178.347-2, plus 178.348-2.

Corrosive lading adds two duties outside the main table. Paragraph (d)(2)(ix) requires the areas covered by the upper coupler, fifth wheel, assembly to be inspected at least once in each two year period for corroded and abraded areas, dents, distortions, defects in welds, plus any other unsafe condition, with the upper coupler assembly removed from the cargo tank for the inspection. Paragraph (d)(4) requires ring stiffeners or other appurtenances on mild steel or high-strength low-alloy steel tanks, which create air cavities adjacent to the tank shell that do not allow for external visual inspection, to be thickness tested at least once every 2 years, with at least four symmetrically distributed readings to establish an average thickness.

What is different in chlorine, propane, or sodium service?

Three dedicated services carry their own rows in the table, plus each one moves the schedule in a different direction. Chlorine service stretches two tests to 2 years. Dedicated propane service on a small MC 331 stretches two tests to 10 years. Dedicated sodium metal service removes the pressure test entirely. The three services share one trait: the tank stays in one service, so the regulation can set the schedule for the service instead of for the general case.

Chlorine service applies to MC 330 and MC 331 cargo tanks. The leakage test runs every 2 years instead of every year, plus the pressure test runs every 2 years instead of every 5 years. The internal visual inspection stays on the 5 year row unless the tank is insulated or the lading is corrosive to the tank. A chlorine tank that also loads by vacuum takes the 2 year pressure test row either way, since both rows set 2 years.

Dedicated propane service is the longest interval in the table. An MC 331 cargo tank with less than 3,500 gallons water capacity, in dedicated propane service, constructed of nonquenched and tempered NQT SA-612 steel, takes an internal visual inspection every 10 years plus a pressure test every 10 years. All three conditions must hold: the size under 3,500 gallons, the dedicated propane service, plus the NQT SA-612 steel. Note 5 extends the 10 year interval to NQT SA-202 or NQT SA-455 steel, provided full-size equivalent Charpy vee notch test data show 75 percent shear-area ductility at 32 degrees F, with an average of 3 or more samples over 15 ft-lb full-size equivalent and no sample under 10 ft-lb full-size equivalent.

The propane exception has a companion rule in the leakage test. Paragraph (h)(1)(ii) lets an MC 330 or MC 331 tank in dedicated liquefied petroleum gas service test at not less than 60 psig, instead of the standard floor of 80 percent of MAWP, plus paragraph (h)(1)(iv) gives the same 60 psig floor to dedicated anhydrous ammonia service. Every other tank tests at no less than 80 percent of the MAWP marked on the specification plate, held for at least 5 minutes.

Dedicated sodium metal service is the only service that removes a test outright. Note 2 to the table states that pressure testing is not required for MC 330 and MC 331 cargo tanks in dedicated sodium metal service, plus paragraph (g)(5)(i) repeats the exception. Sodium metal reacts violently with water, so a hydrostatic pressure test on a sodium tank would be a hazard in itself. The exception covers the periodic pressure test only. Damage that may affect lading retention, or a year or more out of hazardous materials service, still triggers a pressure test under paragraph (b). This tool applies the exception to the periodic row and still flags the pressure test as due now when a condition trigger is answered yes.

Materials that cause corrosion stress cracking carry an extra inspection with the pressure test. Paragraph (g)(3) requires MC 330 and MC 331 tanks built of quenched and tempered steel, or of other steel without postweld heat treatment, in anhydrous ammonia or any service that may cause corrosion stress cracking, to be internally inspected by the wet fluorescent magnetic particle method immediately before and with the pressure test. The same applies to quenched and tempered tanks in liquefied petroleum gas service. Tanks without manholes are excepted, plus the results feed the written report required by section 180.417(c).

Chlorine, propane, ammonia, plus several other tank ladings also sit on the hazardous materials safety permit list. A carrier hauling those materials needs a safety permit as well as a tested tank. The Hazmat Safety Permit Checker works out whether a given material and quantity needs a permit under section 385.403. The Hazmat Placard Checker works out which placards a load requires under section 172.504.

What tests does damage or time out of service trigger?

The periodic schedule is not the only trigger in the section. Paragraph (b) opens with the words without regard to any other test or inspection requirements, then lists conditions that force a test before further use, whatever the calendar says. A tank can be current on every periodic test and still be barred from loading because of a dent, a year in the yard, or a letter from the Department. This tool asks the two condition questions up front because they override the schedule.

The first condition is damage. Paragraph (b)(1) covers a cargo tank showing dents, cuts, gouges, corroded or abraded areas, leakage, or any other condition that might render it unsafe for hazardous materials service. At a minimum, each affected area must be thickness tested under the procedures in paragraph (i), plus evaluated under section 180.411. Any leakage must be repaired under section 180.413. The thickness test here is not the periodic thickness test: it applies to the damaged area specifically, on any tank, lined or unlined, corrosive service or not.

The second condition is damage to lading retention. Paragraph (b)(2) covers a cargo tank that has sustained damage to an extent that may adversely affect its lading retention capability. A damaged cargo tank must be pressure tested under the procedures in paragraph (g). The distinction between (b)(1) and (b)(2) is the severity of the damage: surface damage triggers a thickness test of the area, while damage that may let the lading out triggers a full pressure test.

The third condition is time out of service. Paragraph (b)(3) covers a cargo tank that has been out of hazardous materials transportation service for a period of one year or more. Each such tank must be pressure tested under section 180.407(g) prior to further use. The clock runs on hazardous materials service, not on total time parked: a tank that spent the year hauling non-hazardous loads still triggers the test. A tank bought at auction after a long sit, or a tank brought back after a seasonal layup that stretched past a year, needs the pressure test before its first hazardous load.

The fourth condition is a Department order. Paragraph (b)(5) covers a cargo tank the Department requires to be tested based on the existence of probable cause that the cargo tank is in an unsafe operating condition. Paragraph (b)(4) is reserved. The probable cause trigger is rare, but it means a tank under a compliance review or an investigation can be ordered to test outside the schedule, plus the order carries the same before further use force as the other triggers.

What do the test markings on the tank mean?

Every test that passes leaves a mark on the tank, plus the marks are the fastest way to read the schedule in the yard. Section 180.415 requires each cargo tank that successfully completes the test and inspection requirements in section 180.407 to be marked as specified in the section. The marking is durable and legible, in English, showing the date, month and year, plus the type of test or inspection performed. The markings must be in letters and numbers at least 32 mm, 1.25 inches, high, near the specification plate or anywhere on the front head.

The test types are abbreviated to single letters. V stands for the external visual inspection and test. I stands for the internal visual inspection. P stands for the pressure test. L stands for the lining inspection. T stands for the thickness test. K stands for the leakage test. K-EPA27 stands for a cargo tank tested under paragraph (h)(2), the EPA Method 27 leakage test, after October 1, 2004. The regulation gives three worked examples. The markings 10-99 P, V, L mean that in October 1999 the tank passed the pressure test, the external visual inspection and test, plus the lining inspection. The markings 2-00 K, K-EPA27 mean that in February 2000 the tank passed the leakage test under both the standard method in paragraph (h)(1) plus EPA Method 27 in paragraph (h)(2).

The markings tell a buyer or an inspector the test history at a glance, but they show the month and year, not the day. A tank marked P 06-21 passed its pressure test sometime in June 2021. The 5 year pressure test falls due in June 2026, plus the exact day comes from the test report, not from the plate. This tool asks for full dates because the due date arithmetic needs the day. When only the marking is available, use the first day of the marked month as the last test date to stay conservative, then confirm the exact date from the report.

Multi-tank vehicles have their own marking rule. Paragraph (c) states that for a vehicle composed of multiple cargo tanks of the same specification, tested and inspected at the same time, one set of markings may be used. For a vehicle with tanks of different specifications, tested at different intervals, the markings must appear in the order of each tank location, from front to rear.

What records must you keep after each test?

Every test generates a written report, plus the reports are the paper trail that proves the schedule was kept. Section 180.417(b) requires each person performing a test or inspection under section 180.407 to prepare a written report, in English. The report must show the owner plus manufacturer serial number, the manufacturer name, the DOT or MC specification number, the MAWP, whether the tank is lined, insulated, or both, plus any special service, such as corrosive lading or dedicated service.

Each report must also show the test type, the date, month and year, a listing of all items tested or inspected, including pressure relief device and upper coupler information plus the leakage and pressure test method, fluid, pressure, plus holding time, the location of defects plus the method of repair, the repair facility authorization number when applicable, the name and address of the person performing the test, the facility registration number, a continued qualification statement, the DOT registration number of the Registered Inspector, plus the dated signature of the Registered Inspector and the cargo tank owner.

Retention is tied to the next test, not to a fixed number of years. Paragraph (b)(3) requires the owner and the motor carrier, when not the owner, to each retain a copy of the test and inspection reports until the next test or inspection of the same type is successfully completed. A 5 year pressure test report is kept for 5 years, until the next pressure test passes. A 1 year leakage test report is kept for a year. The requirement does not apply to a motor carrier leasing a cargo tank for fewer than 30 days.

The manufacturer certificate lives longer. Paragraph (a)(1) requires each owner of a specification cargo tank to retain the manufacturer certificate, the manufacturer ASME U1A data report where applicable, plus related papers certifying that the tank was manufactured and tested under the applicable specification, throughout ownership of the tank plus one year thereafter. When ownership changes, the prior owner must retain non-fading photo copies of the documents for one year. Paragraph (d) requires each person offering a DOT specification cargo tank for sale or lease to provide the purchaser or lessee a copy of the certificate of compliance, repair records, plus the most recent inspection and test reports.

MC 330 and MC 331 tanks in ammonia, LPG, or stress corrosion cracking service carry an extra report. Paragraph (c) requires the carrier, after each pressure test in section 180.407(g)(3), to file a written report covering the carrier identity, the plate data, the equipment number, whether the tank was stress relieved after fabrication, the tester plus the test date, the nature and location of any defects, the repairs made plus who made them, the disposition of the tank, plus the service history, including whether each ammonia shipment since the last report was certified as containing 0.2 percent water by weight. A copy is kept at the principal place of business while the tank is in service plus one year thereafter.

Only a qualified inspector may perform or witness these tests. Section 180.409 sets the minimum qualifications for a Registered Inspector, plus section 180.411 sets the acceptable results the inspector evaluates the tank against. A test performed by an unqualified person does not satisfy the section, whatever the result. Owners should confirm the inspector registration number on the report matches a current Registered Inspector.

Training runs alongside the test schedule. Section 177.816 requires driver training for hazmat drivers, including specialized cargo tank training covering compartmented tanks, partial load stability, plus retest and inspection requirements. The Hazmat Training Tracker works out training due dates plus record retention under section 172.704, so the driver qualification stays current alongside the tank schedule.

How is the tank test schedule different from the annual vehicle inspection?

The tank tests and the vehicle inspection are two separate requirements, run under two different parts of the regulations, on two different clocks, plus passing one does not satisfy the other. The tank tests run under Part 180, which covers the continuing qualification and maintenance of packagings, plus they test the cargo tank itself: the shell, the heads, the lining, the valves, plus the relief devices. The annual vehicle inspection runs under section 396.17, which covers the periodic inspection of commercial motor vehicles, plus it tests the vehicle: the parts and accessories listed in Appendix G to Subchapter B, including brakes, steering, lighting, tires, plus the frame.

Section 396.17(c) states that a motor carrier must not use a commercial motor vehicle unless each component identified in Appendix G has passed an inspection in accordance with the section at least once during the preceding 12 months, plus documentation of the inspection is on the vehicle. The documentation may be the inspection report prepared under section 396.21(a), or another form based on the report, such as a sticker or decal, showing the date of inspection, the entity where the report is maintained, information identifying the vehicle, plus a certification that the vehicle passed.

The two schedules overlap in practice but never merge. A tractor pulling a DOT 406 trailer needs the annual vehicle inspection on the tractor, the annual vehicle inspection on the trailer as a commercial motor vehicle, plus the tank tests on the cargo tank. The trailer inspection and the tank external visual inspection may happen on the same visit to the shop, but they are different inspections, performed by different qualified people, recorded on different forms, plus marked in different places. Confusing the two is how a carrier ends up with a current annual inspection sticker and an overdue pressure test.

The daily checks sit on a third clock. The driver vehicle inspection report under section 396.13 covers the daily pre-trip and post-trip inspection of the vehicle, plus the pre-trip inspection of a cargo tank vehicle includes the tank fittings, valves, plus visible damage that could trigger a paragraph (b) test. The DVIR Checker covers the daily vehicle inspection report plus the defects it must record. The Pre-Trip Inspection Checklist covers the pre-trip inspection step by step. A driver who spots a dent, a cut, a corroded area, or a leak on the pre-trip inspection has found a paragraph (b)(1) condition, plus the tank needs testing before further use, whatever the periodic schedule says.

Track both schedules together. The Annual Inspection Due-Date Tracker works out when the next periodic inspection falls due under section 396.17, so the truck inspection stays current alongside the tank schedule. Run both tools on the same day each month: the tank tool for the cargo tank tests, the annual inspection tool for the vehicle inspection, plus the training tracker for the driver. The three together cover the tank, the truck, plus the driver, which is the whole compliance picture for a tanker operation.

How do you use the Cargo Tank Inspection Schedule?

Work through the fields in order: the tool updates with every change, so you can fix an answer and watch the schedule change.

  1. Pick the cargo tank specification from the plate.
  2. Answer the service questions: vacuum loading, insulation, lining, plus lading.
  3. Enter the CTMV certification date and the last test dates.
  4. Set the check date to today.
  5. Read the next due date for each test.
  6. Book any overdue test before the tank is filled again.

Use dates from the test reports, not from memory: the tank marking shows only the month and year each test passed, while the due date arithmetic needs the exact day. When only the month and year are available, use the first day of the marked month, then confirm the exact date from the report. Read the earliest due test first: it governs the tank, plus when it is due now the tank is already barred from loading and the booking is urgent.

Questions drivers ask

How often must a cargo tank be inspected?

Every year for the external visual inspection and the leakage test, every 5 years for the internal visual inspection and the pressure test, every year for the lining inspection on lined tanks carrying corrosive lading, every 2 years for the thickness test on unlined tanks carrying corrosive lading, plus every 5 years for the heating system test where a heating system is fitted. The intervals shorten for vacuum-loaded tanks, insulated tanks, corrosive lading, plus chlorine service, plus stretch to 10 years for a small MC 331 propane tank, all under 49 CFR 180.407(c).

What does the V marking on a cargo tank mean?

V stands for the external visual inspection and test, under 49 CFR 180.415. The marking pairs the letter with the month and year the test passed, in letters at least 32 mm (1.25 in) high, near the specification plate or anywhere on the front head. The other letters are I for internal visual inspection, P for pressure test, L for lining inspection, T for thickness test, K for leakage test, plus K-EPA27 for a leakage test under EPA Method 27.

Can a cargo tank be filled when a test is overdue?

No. Under 49 CFR 180.407(a)(1), a cargo tank for which a test or inspection has become due may not be filled and offered for transportation or transported until the test has been successfully completed. The one exception covers a tank filled before the due date: that load may finish its trip, but the tank may not be filled again until the test passes.

How often does an MC 331 propane tank need a pressure test?

Every 10 years, when the tank is under 3,500 gallons water capacity, in dedicated propane service, plus constructed of nonquenched and tempered NQT SA-612 steel, under the table in 49 CFR 180.407(c). The same 10 year interval applies to the internal visual inspection. The interval also covers NQT SA-202 and NQT SA-455 steel with qualifying Charpy vee notch test data. Any other MC 331 takes the pressure test every 5 years.

What is the difference between the tank tests and the annual vehicle inspection?

The tank tests under 49 CFR 180.407 check the cargo tank itself: shell, heads, lining, valves, plus relief devices, on intervals from 6 months to 10 years. The annual vehicle inspection under 49 CFR 396.17 checks the commercial motor vehicle: brakes, steering, lighting, tires, plus frame, at least once every 12 months. Passing one does not satisfy the other. A tanker needs both current.

What happens if a cargo tank fails a test?

Under 49 CFR 180.407(a)(6), the owner must repair the tank and retest it under section 180.413, or remove it from hazardous materials service and remove, obliterate, or cover the specification plate in a secure manner. A failed tank may not keep hauling while the owner decides. A tank below minimum thickness may keep working only at reduced weight or pressure, certified by a Design Certifying Engineer, or not at all.